The location of the plant is a crucial parameter that can affect the
profitability of the project and scope for future expansion
6.1Factors for Site Selection:
6.11 Nation’s Interest
6.12 Profitability of the project
6.13 Productivity of the project
6.11 Nation’s Interest
6.111 Dispersal of Industries
India is an industrially diverse country. Certain pockets are
industrially well developed and some are backward. Location of the plant in an
industrially prosperous region may be advantageous but may add to tremendous
pressure on civic amenities like water, power in that region. Therefore,
dispersal of industries is important.
6.12Profitability of project
6.121 Raw Material Availability
Transportation and handling are the major contributors to cost of
the raw materials. Thus a site must be selected such that the raw materials are
available in the vicinity.
The raw materials for the selected process are ethylene oxide and
carbon dioxide. Hence proximity to a petrochemical complex is preferable. In India the major
producers of ethylene oxide are
·
Reliance Industries Limited,
Hazira (Gujarat)
·
NOCIL, Thane-Belapur (Maharashtra)
·
India Glycols Limited, Kashipur
(Uttarpradesh)
6.122. Market for Finished
Product
The final product ethylene carbonate has a good market potential in India as well
as abroad. So proximity to a port is essential.
6.123 Land
Keeping
in mind the size and the capacity of the plant, the cost of land required is
not going to play an important role in the actual selection of the site.
6.124 Soil Survey
This includes the type of soil, its bearing capacity, identification
of seismic zone and height of water table. Neglect of this parameter may lead
to mechanical breakdown of the plant.
6.125 Climatic Conditions
The necessary climatic data like average rainfall, minimum and maximum
temperature, frequency of cyclones and hurricanes should be considered while
selecting a site.
6.126 Environmental Issues
Present state of environment, proximity to archaeological/historical
site, density of population are some factors that come under environmental
issues.
6.127 Supports from State Government
This factor is also very important especially in a country like India where red
tapism and corruption are rampant. This can play a very important role in
deciding the speed with which the work is going to progress.
6.128 Fabrication facilities
The fabrication facilities in the site and nearby areas are also
important to speed up the plant construction.
6.13 Productivity of the
Project:
6.131 Source of Water
In the selected process there is, as such no consumption of water
(process water). Utilities, maintenance, etc consume water. The site should
have a continuous supply of water either from a tube well or river or sea or
state industrial development corporation.
6.132 Power
The continuous supply of power is essential for the productivity of
the plant. Power can be obtained from the state electricity grid.
6.133 Labour
The kind of labour available is going to play a very important role
because finally the work has to be done by the labourer and it is his attitude
that is going to matter.
6.134 Infrastructure
The site should be accessible by road, rail and air. Not much amount
can be afforded for building infrastructure in this project. Existence of a
good infrastructure is important.
Based on all the
factors mentioned above, three sites are proposed.
A) Hazira B) Thane-Belapur
C) Kashipur
The above sites are evaluated on a scale of 10.